Flat Roof Repairs - Paula Radcliffe Pavilion (103) 16th - 30th September 2024

Posted: 6 August 2024

WHY DOES THE WORK NEED TO BE DONE

The work comprises the renewal of the felted flat above the club room to solve an ongoing leak.

HOW WILL THE WORKS AFFECT ME?

The programme for the works is as follows:

  1. Scaffold Erection - 16th – 18th September. 
  2. Roofing Works - 19th - 26th September.      
  3. Scaffold Dismantling - 27th – 30th September.

Access to the building will be maintained during the works period; however, there may be access restrictions when the scaffolding is being erected / dismantled as operatives will be working overhead.

TIMESCALE

16th – 30th September

Working hours are from 0800 to 1700.

How can I get more information and help?

The Estates and Facilities Management team member looking after the task is detailed below and can be contacted about any difficulties experienced because of these works.

Craig Lord / Spencer Aryeetey– Building Fabric Surveyors

Mobile:  07729 080 151 / 07977 004 475