Charnwood Immersion Replacement - Charnwood Building (Core B) (055) - Tuesday 20 August 2024 - All Day

Posted: 16 August 2024

Description of the works

An immersion heater on a calorifier has become defective and needs replacing.

To carry this out, the calorifier will need draining and will take a few hours because of the volume.

While draining, the system will be isolated, and those in Core B will only have cold water at points of use.

As soon as draining is complete, the new immersion will be fitted and the system will be re-filled.

Timescale

Tuesday 20 August 2024 for the whole day

How can I get more information and help?

The Estates and Facilities Management team member looking after the task is detailed below and can be contacted about any difficulties experienced because of these works.

Tony Dalley - Mechanical - Holywell Park Lead

Mobile - 07895331899